Construction Update June 2017: Southern Corridor Improvements
Welcome to the June 2017 construction update for the
New Zealand Transport Agency's
Southern Corridor Improvements Project
This update
outlines what works we achieved in May and provides details on what we have
planned for June. Photos of progress are provided at the bottom of the update.
PROGRESS THROUGH MAY
Early in the
month, a major project milestone was achieved when the additional 3rd
southbound lane was opened to motorists from Hill Road to the Takanini
off-ramp; and from the Takanini on-ramp to the Pahurehure Inlet. The lane has
improved southbound traffic flow during peak hours. Narrowed lanes and a
reduced speed limit will remain in place while improvements continue in other
areas of the project.
Later in the
month, demolition of the Orams Road Bridge was completed when large deck
sections were removed. Construction of the new bridge abutment began with the
installation of 20 piles that will provide support for the extended bridge
structure.
More detail
about works completed in May include:
Orams Road Bridge:
- The eastern span of Orams Road
Bridge was demolished. Concrete and wire saws were used to cut sections of
the deck, and a large crane lifted each section onto trucks for site
removal.
- Flat platforms were constructed
to improve access for workers to build the new bridge pier.
- Piling work for the new eastern
abutment was completed. Steel pipes and concrete were inserted in 20
pre-drilled holes to form support structures for the bridge foundation.
- South of the Orams Road Bridge,
vegetation clearance continued to prepare the area for a new wetland pond
which will help filter motorway run-off.
Hill Road to the Takanini Interchange:
- An additional southbound lane
was opened from Hill Road to the Takanini Interchange off-ramp.
- In the southbound shoulder
from Alfriston Road Bridge to the Takanini Interchange, noise wall
installation continued, and swales and check dams
were constructed. Check
dams slow the flow of water and filter out larger materials in
swales.
- In the median, construction of
slipform barriers continued between the northbound and southbound lanes.
This is scheduled for completion early June.
Takanini
Interchange:
- Scour protection continued
along the banks of the Papakura Stream near the new bridge abutments.
Soil was removed and replaced with rocks to reduce the risk of
erosion and ensure stability of the stream bank.
- On the northbound shoulder
between Great South Road and the railway line, sheet piling continued
to prepare the area for upcoming works on the additional lane and extended
northbound on-ramp.
- Along the southbound shoulder,
piling pads have been constructed to provide a stable surface for
machinery to install piles at the new SH1 southbound bridge over
Great South Road.
- Construction access was
established off Great South Road into the existing northbound on-ramp
loop. Using this new access, vegetation clearance was completed inside the
loop.
Takanini Interchange
to Papakura Interchange:
- Asphalting was completed in the
southbound shoulder from the Takanini Interchange to the Pahurehure Inlet.
Lanes were marked and temporary barriers were shifted to allow motorists
access to the new additional southbound lane.
- Noise wall installation
continued along the northbound and southbound shoulders from the
Pahurehure Inlet to Takanini Interchange.
- Pavement works were
completed in the median between the Pahurehure bridge and Pahurehure
culvert. This work involved compaction of granular materials and asphalt
layers.
UPCOMING WORK IN
JUNE
Work over the next month will focus on
constructing the new abutment, span and deck at the Orams Road Bridge. The
new abutment piles will be capped prior to installing the beams. Once the
bridge beams are installed, construction on the new bridge deck will begin.
To add an additional northbound lane and
lengthen the northbound on-ramp at Takanini Interchange, six northbound bridges
will be constructed. Two bridges will guide traffic across Great South Road,
the railway line, and Papakura Stream. Piling works will continue and will
provide a safe work area for further road construction.
More details about upcoming works this
month include:
Orams Road
Bridge:
- Substructure work will
continue. Installation of steel reinforcement bars and formwork will
allow a concrete capping beam to be poured on top of the piles. The
concrete will be poured first in the mid-section, followed by the north
side, and finally the south side of the bridge.
- When the capping beam has
cured, bearing pads will be installed to support the steel beams of the
bridge deck which will be installed late June.
Hill Road to the
Takanini Interchange:
- Slipform median barriers will
continue to be constructed between Hill Road and the Papakura Stream.
Following barrier construction, new median light poles will be installed.
- In the southbound shoulder from
Alfriston Road Bridge to the Takanini Interchange, the noise wall panels
will be painted. Drainage work will be completed, including swale and
check dam installation. Following this work, permanent guard rails will be
installed, and the temporary barriers removed.
Takanini Interchange:
- In the northbound shoulder at Papakura Stream,
hollow core concrete beams will be installed on the bridge deck and will
begin to form both the new northbound on-ramp
and additional 3rd traffic lane.
- Along the northbound shoulder between Great South
Road and the railway line, sheet piling will be completed. Following sheet
piling, soil nails will be installed to reinforce the bank prior to the
construction of a retaining wall.
- In the eastbound and westbound shoulders along
Great South Road, service relocation will begin to move services deeper
underground.
Takanini to Pahurehure Inlet:
- Noise wall construction will continue in the
northbound shoulder from the Pahurehure Inlet to Takanini Interchange. In
the southbound shoulder, permanent guardrails will be installed and the
temporary barriers will be removed.
- Between the Pahurehure bridge and Pahurehure
culvert, southbound motorway traffic will shift towards the median,
allowing a safe work zone to be established in the southbound shoulder.
Following the traffic switch, earthworks will commence in the shoulder to construct
the additional southbound lane.
- At the Pahurehure culvert, a new safe work zone
will be established in the median (location shown in pictures below). This
will allow crews to begin widening the culvert. The existing median
abutment will be demolished and removed before being replaced.

The Pahurehure culvert - In June concrete barriers
will be placed to create a safe work zone in the median for crews to demolish
and remove the existing abutment. Just north of the culvert, crews have
finished work in the median allowing southbound traffic to shift into the
median. This establishes a safe work area in the southbound shoulder and allows
widening works to begin.
Sheet piling in the northbound shoulder, between Great
South Road and the railway line, will be complete early June. This supports the
existing bank and northbound lanes while crews work to
construct a MSE.
At the Papakura Stream, work continues
along the stream banks to increase stability and protect them from eroding.
Bridge abutments have been completed, and bridge beams for the
northbound bridges will be lifted into place in June.

Prior to demolishing the Orams Road Bridge towards the end of May, 20
piles were constructed to support the new eastern abutment.

View from Alfriston Road
Bridge, looking south with the additional 3rd southbound lane open
to motorists. Crews are working to complete the permanent median slipform
barriers, and the drainage works in the southbound shoulder.
With narrowed lanes, there
is less time to react to other vehicles and it is important that
motorists keep to the posted 50-80 km/h speed limits past our
work areas. There will be ongoing truck and project vehicle movements accessing
the shoulder and the median work sites. Keeping both motorists and our team
members as safe as possible is imperative and we need everyone's help to do
this.
As always, we will be
doing our best to minimise effects of these works on motorists as much as we
can. We thank you for your patience as we work to improve journey reliability
and safety along the Southern Corridor.
You can read more
background information and find out more about the project through our
website, www.nzta.govt.nz/auckland-southern-corridor.