
Welcome to the May 2017 construction update for the New Zealand
Transport Agency's
Southern Corridor Improvements Project
This update outlines what works we achieved in April and provides
details on what we have planned for May. Photos of progress are provided at the
bottom of the update.
PROGRESS THROUGH APRIL
On Saturday 1 April, the new southbound off-ramp at Takanini was connected to the motorway by stitching the new and existing bridges over Papakura Stream together with concrete. The off-ramp was opened to traffic on the 20 April. Following this, the third southbound lane from Hill Road to Takanini was opened to traffic on Sunday 23 April. Reduced speed limits and narrowed lanes will remain in place while we complete works between Orams Road and Hill road, along the southbound shoulder and at the Takanini Interchange.
Orams Road Bridge was closed to all traffic starting on Saturday 22
April until October 2017. Signposted traffic detour routes are in place along
Everglade Drive, Redoubt Road and Great South Road, while the pedestrian and
cyclist path can be accessed via the Puhinui Stream Bridge underpass (off
Everglade Drive from inside the Botanic Gardens). More information about the
closure can be found on our website http://nzta.govt.nz/projects/southern-corridor-improvements/media.
Safe work zones were installed along Great South Road near the Takanini Interchange. This allows crews to safely upgrade the Interchange bridges, and construct the new northbound on-ramp.
Below is a summary of our activities in April:
Orams Road to Takanini Interchange:
Takanini Interchange
Takanini Interchange to Pahurehure Inlet:
UPCOMING WORKS IN MAY
Throughout May, the project will continue to focus on constructing the additional third lane southbound from the Takanini on-ramp to the Pahurehure Inlet. This lane is scheduled to open to traffic later this month.
On the Orams Road bridge, work will continue to demolish and remove the eastern span and abutment. Piling for the new abutment will follow demolition.
With safe work zones in place at the Takanini Interchange, piling for multiple structures will begin to upgrade the overpass over Great South Road and the northbound on-ramp and off-ramp.
Below is a summary of what we have planned for May:
Orams Road to Takanini Interchange:
Takanini Interchange:
Takanini Interchange to Pahurehure Inlet:
Pahurehure Inlet to Papakura Interchange:

When building roads, layers of granular materials are spread and
compacted to stabilise the ground prior to asphalting. Above shows a sub-base
rock layer being compacted in the southbound shoulder adjacent
to Conifer Grove.

After the coarse layer has been compacted,
fine layers of smaller rocks, stones, sand and gravel are spread and compacted.
Above shows this stage of pavement works in the median, near Alfriston Road
Bridge.

The top surfaces of the road are made up
of asphalt concrete layers. Each has unique characteristics that reduce tire
wear and roadway noise while also prolonging the life of the motorway. Above
shows asphalt and line marking in the median near Alfriston Road Bridge.
Additional layers and
improved compaction will allow the motorway to handle heavier loads and more
traffic over a longer time. Above shows three lanes southbound at
Alfriston Road Bridge, asphalted and linemarked for traffic.
Noise walls south of
Takanini Interchange continue to be installed along the northbound and
southbound shoulders of the motorway. North of Takanini to Hill Road, noise
wall installation has been completed on the southbound shoulder. Painting of
the motorway side of the noise walls will begin this month.

In the coming months, work will ramp up around the Takanini Interchange. Construction is already underway on the eight bridges in the area and the new loop for the northbound on-ramp.
With the narrowed lanes, there is less time
to react to other vehicles and it is important that motorists keep to
the 80 km/h speed limit past our work areas. There will be
ongoing truck and project vehicle movements accessing the shoulder and the
median work sites. Keeping both motorists and our team members as safe as
possible is imperative and we need everyone's help to do this.
As always, we will be doing our best to minimise effects of these works on motorists and the community as much as we can. We thank you for your patience as we work to improve journey reliability and safety along the Southern Corridor.
You can read more background information and find out more about the project through our website, www.nzta.govt.nz/auckland-southern-corridor.
If you have any questions or queries, please contact our team on free phone 0508 NZTA SCI (0508 698 2724) or email us at southerncorridor@nzta.govt.nz. Also feel free to visit us at the Project Office located at 8 Great South Road, Takanini.