
Welcome to the April 2017
construction update for the New Zealand Transport Agency's
Southern Corridor Improvements
Project
This update outlines what works we achieved in March and provides details on what we have planned for April. Photos of progress are provided at the bottom of the update.
PROGRESS THROUGH MARCH
Despite the wet weather over the last month, we continued to focus on completing the additional southbound lane from the Hill Road off-ramp to the Takanini off-ramp, and between the Takanini on-ramp and Pahurehure Inlet.
At Takanini, temporary lane changes southbound enabled the establishment of a safe work zone for bridge works over Papakura Stream. By breaking the concrete edge of the old bridge, the area was ready for concrete to be poured and the old and new bridges were connected together.
We continued installing temporary traffic management northbound from the Papakura Interchange to Pahurehure Inlet. With narrowed lanes and an 80kph reduced speed limit established both northbound and southbound, the work zone has been extended to accommodate safe works in the median.
Below is a summary of our activities in March:
Hill Road to Takanini Interchange:
Takanini Interchange to Pahurehure Inlet:
UPCOMING WORKS IN APRIL
Final works along the additional third southbound lane will be complete before it opens to traffic later this month. On SH1 southbound, the additional lane will run from the Hill Road off-ramp to the Takanini off-ramp, and between the Takanini on-ramp and 300m north of the Pahurehure Inlet. Reduced speed limits and narrowed lanes will remain in place while we complete works along the shoulders and at the Takanini Interchange.
The new Takanini southbound off-ramp was connected to the existing bridge on the 1st April. For this to take place, a 12 hour southbound motorway closure was necessary to allow the poured concrete to cure and gain sufficient strength and avoid vibration from passing vehicles.
Orams Road Bridge will be closed to all traffic from Saturday 22 April until October 2017. The eastern span of the bridge needs to be demolished and a longer span constructed in order to widen the SH1 southbound carriageway for an additional fourth lane from SH20 to Hill Road. More information about the closure can be found on our website http://nzta.govt.nz/projects/southern-corridor-improvements/media under the heading Updates.
Below is a
summary of what we have planned for April:
Hill Road to Takanini Interchange:
Preparation for the demolition of Orams Road Bridge begins.
Work continues under Alfriston Road Bridge. This includes laying permanent asphalt, pouring concrete to create new median barriers and installing a new southbound gantry. We will also complete new drainage lines under the motorway.
Asphalting continues in the southbound shoulder. This is one of the last activities prior to opening the additional (third) southbound lane from Hill Road to Pahurehure Inlet (excluding Takanini).
Earthworks and drainage continue along the southbound shoulder.
The new Takanini southbound off-ramp was connected to the existing Papakura Stream Bridge during an overnight concrete pour on Saturday 1 April.
At the northbound Papakura Stream Bridge, sheet piling will occur to prepare for the construction of new bridge abutments.
Takanini Interchange:
Takanini
Interchange to Pahurehure Inlet:
Pahurehure
Inlet to Papakura Interchange:
PROGRESS PHOTOS

Box cut in the median at Alfriston Road Bridge looking
south. The previously grassed median has been excavated and new materials have
been compacted, prior to asphalting.

New
noise wall panels and subsoil works preparing the southbound lanes for
asphalting. Asphalting is now almost complete. This is one of the last
activities required before opening the new additional (third) lane from Hill
Road to the Takanini southbound off-ramp and from the Takanini southbound
on-ramp to Pahurehure Inlet.

At the start of April, the new Takanini
southbound off-ramp was connected to the existing southbound bridge. On the
northern side of the motorway, works have begun in Fergusson Reserve to prepare
for the new Takanini northbound on-ramp.

A
major milestone for the team in March was the completion of the retaining wall
along the new southbound off-ramp at the Takanini Interchange, over the rail
carriageway.

The new southbound off-ramp at Takanini
Interchange will be open to traffic towards the end of April.

Orams Road Bridge will be closed for
five months from 22 April until October 2017, in order to demolish the eastern
span and construct a longer bridge deck to accommodate four southbound motorway
lanes.

Traffic
management was installed southbound and northbound between Papakura Interchange
and Pahurehure Inlet to enable earthworks to begin in the median.
With narrowed
lanes, there is less time to react to other vehicles and it is important that
motorists keep to the 80 km/h speed limit past our work areas. There
will be ongoing truck and construction vehicle movements accessing the shoulder
and the median work sites. Keeping both motorists and our team members as safe
as possible is imperative and we need everyone's help to do this.
As always, we will be doing our best to minimise effects of these works on motorists as much as we can. We thank you for your patience as we work to improve journey reliability and safety along the Southern Corridor.
You can read
more background information and find out more about the project through the NZTA website, www.nzta.govt.nz/auckland-southern-corridor.
If you have any questions or queries, please contact our team on free phone 0508 NZTA SCI (0508 698 2724) or email us at southerncorridor@nzta.govt.nz. Also feel free to visit us at the Project Office located at 8-12 Great South Road, Takanini.