Home / News / Article

Bus and Coach Association Notifications



Construction Update March 2017 - Southern Corridor Improvements

nzta.PNG.jpg
Wednesday, 8 March 2017

 

Welcome to the March 2017 construction update for the New Zealand Transport Agency's

Southern Corridor Improvements Project

 

PROGRESS THROUGH FEBRUARY

Over the last month, work continued to focus on constructing the additional (third) southbound land from the Hill Road off-ramp to the Takanini off-ramp, and between the Takanini on-ramp and 300m north of the Pahurehure Inlet.

We also installed temporary traffic management to extend our median work zone from the Pahurehure Inlet to the Papakura Interchange. On the southbound side, lane are now narrowed and a 80kph reduced speed limit was established on the morning of Wednesday 15 February.

Work included:

Manukau Interchange to Hill Road:

  • Under the Hill Road Bridge, the southbound concrete bridge pier protection wall was completed.

Hill Road to Takanini Interchange:

  • Retaining wall and noise wall construction continued along the southbound side of the motorway between Alfriston Road and the Takanini Interchange.
  • Asphalting operations continued to form the new lane on the southbound shoulder between Alfriston Road and the Takanini Interchange.
  • Light installation continued along the median.
  • Under the Alfriston Bridge, drainage and pavement works continued.

 

Takanini Interchange to the Pahurehure Inlet:

  • Retaining wall and noise wall construction continued along the southbound side of the motorway.
  • Earthworks and drainage continued along the southbound shoulder in preparation for pavement layers. This also included shaping of the new open channels (also known as swales), which help treat stormwater as it runs off the motorway.
  • Vegetation clearance continued along the northbound shoulder in preparation for drainage works and noise wall construction.

 

Pahurehure Inlet to Papakura Interchange:

  • Lanes were shifted to the southbound shoulder in preparation for the new median work zone.

Other Areas:

  • On the Papakura Stream Bridge, bridge deck construction, earthworks and drainage works continued (please see the attached photo).
  • At bridges crossing the railway line and on the Spartan Road Bridge, deck and retaining wall construction continued.
  • Offsite production of precast components for retaining walls, noise walls, and bridges continued.

WORK BEING UNDERTAKEN IN MARCH

March will focus on completing the additional southbound lane from the Hill Road off-ramp to the Takanini off-ramp, and between the Takanini on-ramp and 300m north of the Pahurehure Inlet. This will see work continuing in the median and shoulders between Hill Road and the Papakura Interchange in the coming month. 

From Monday 6 March, lane one (the slow lane) will be separate from lane two to create a safe work area (please see the attached picture). This will allow our construction team to continue widening the motorway.

Around mid-March, we will install temporary traffic management to extend our safe work zone from the Pahurehure Inlet to the Papakura Interchange. This will include narrowed lanes and a 80kph reduced speed limit on the northbound side. Work will also continue on widening the motorway bridges over the Papakura Stream and the KiwiRail Lines.

Work this month will include:

Manukau Interchange to Hill Road:

  • Under Hill Road, the northbound bridge pier protection wall will continue construction.

Hill Road to the Takanini Interchange:

  • Under Alfriston Road, drainage and pavement works continue to prepare for pavement layers. Construction of slip form barriers will commence shortly after the completion of pavement works.
  • Retaining wall and noise wall construction continue along the southbound side of the motorway between Alfriston Road and the Takanini Interchange.
  • Asphalting will continue along the southbound shoulder between Alfriston Road and Takanini Interchange.

Takanini Interchange to Pahurehure Inlet:

  • Vegetation clearance will resume along the northbound side.
  • Earthworks and drainage continues along the southbound shoulder in preparation for pavement layers. This also includes shaping of the new open channels (also known as swales), which help treat stormwater as it runs off the motorway.
  • Retaining wall and noise wall construction continued along the southbound side of the motorway.
  • Asphalting will continue along the southbound shoulder between Takanini Interchange and the Pahurehure Inlet.

Pahurehure Inlet to Papakura Interchange:

  • Pavement works begin to level the pavement along the northbound shoulder. This will allow traffic to shift to the northbound shoulder and a new median work zone will be established.

Other Areas:

  • On the Papakura Stream Bridge, bridge deck construction, earthworks and drainage works will continue. This includes shaping of the new open channels (also known as swales), which help treat stormwater as it runs off the motorway.
  • At bridges crossing the railway line and on the Spartan Road Bridge, deck and retaining wall construction will continue.
  • Offsite production of precast components for retaining walls, noise walls, and bridges continue

With the narrowed lanes, there is less time to react to other vehicles and it is important that motorists keep to the 80 km/h speed limit past our work areas. There will be ongoing truck and project vehicle movements accessing the shoulder and the median work sites. Keeping both motorists and our team members as safe as possible is imperative and we need everyone's help to do this.

As always, we will be doing our best to minimise effects of these works on motorists as much as we can. We thank you for your patience as we work to improve journey reliability and safety along the Southern Corridor.

You can read more background information and find out more about the project through our website, www.nzta.govt.nz/auckland-southern-corridor.


Bus Jobs NZ
Get a great job that
will take you places!
View job vacancies.
Copyright © 2018 Bus and Coach Association New Zealand Inc - Sitemap - Admin Login - Website by Welman Technologies