Traffic Notice 3 - 9 March: Southern Corridor Improvements

nzta.PNG.jpg
Friday, 3 March 2017

Welcome to the traffic notice for the week of 3 - 9 March for the

Southern Corridor Improvements Project

 

Traffic notices provide a brief overview of likely traffic disruptions for the following week. Full closures are also advertised in the Weekend Herald. Traffic notices are complemented by monthly construction updates and quarterly newsletters. 

ALREADY IN PLACE

  • Narrowed lanes and 80 km/h speed limit northbound between the Pahurehure Inlet and Hill Road.
  • Narrowed lanes and 80 km/h speed limit southbound between Orams Road and the Papakura Interchange.

Update: Due to unexpected circumstances, there has been a further adjustment to the timeline for the northbound lane changes between the Papakura Interchange and Pahurehure Inlet. The work will now take place on the nights of Wednesday 8 March to Thursday 9 March and resume on Monday 13 March to Tuesday 14 March from 9pm-5am. Lanes will be narrowed and a reduced speed limit of 80kph will be in effect from the morning of Friday 10 March for approximately one year.

TRAFFIC NEXT WEEK

Northbound:

  • Sunday 5 March - Tuesday 7 March - Night closure of the full northbound motorway between the Takanini Interchange and Hill Road. This includes closure of the northbound Takanini on-ramp (Great South Road).
  • Wednesday 8 March and Thursday 9 March - Night closure of the full northbound motorway between the Papakura Interchange through to the Takanini Interchange. This includes closure of the northbound Papakura on-ramps.

Southbound

  • Friday 3 March - Night closure of a single lane southbound on the motorway between Hill Road to the Takanini Interchange.
  • Sunday 5 March - Wednesday 8 March - Night closure of the full southbound motorway between the Manukau Interchange through to the Takanini Interchange. This includes closure of the Redoubt Road on-ramp, Lambie Drive eastbound on-ramp, and SH20-1 Link.  

UPCOMING WORKS (dates may be subject to change)

  • Sunday 12 March - Thursday 16 March - Night closure of a single lane southbound between the Takanini Interchange through to the Papakura Interchange.
  • Monday 13 March - Wednesday 15 March - Night closure of the full northbound motorway between the Papakura Interchange through to the Takanini Interchange. This includes closure of the northbound Papakura on-ramps.
Night work on the motorway next week involves earthworks in the median underneath Alfriston Road Bridge and asphalting over Papakura Stream Bridge southbound. We will also be moving barriers and line marking to extend our work zones in the southern most part of the project. On the Papakura Stream Bridge, we will create a new work zone in preparation to connect the old and new southbound bridges together (please see the attached photo). At the Papakura Stream Bridge northbound, sheet piling will commence to retain the surrounding soil during bridge construction. If it rains or ground conditions are too wet, work will be postponed until the next available dry night.

Work during the night will allow our crews to operate equipment safely while adjacent to the existing traffic lanes. Work in the shoulder and median work zones will continue during the daytime next week, but this will not affect traffic movements.

Night closures are typically from 9pm at night to 5am in the morning. Detours will be in place to take motorists along local roads, leading back to the next motorway interchange. All detours will be clearly signposted, and maps of the typical routes can be found on our website at http://www.nzta.govt.nz/projects/southern-corridor-improvements/traffic-notices/.  Please allow extra time for your journey at night.

With the lanes narrowed, there is less time to react to other vehicles and it is important that motorists keep to the 80 km/h speed limit past our work areas. There will be ongoing truck and project vehicle movements accessing the shoulder and median work sites. Keeping both motorists and our team members safe as possible is imperative and we need everyone's help to do this.

As always, we will be doing our best to minimise effects of these works on motorists as much as we can.

We thank you for your patience as we work to improve journey reliability and safety along the Southern Corridor.

You can read more background information and find out more about the project through our website, www.nzta.govt.nz/auckland-southern-corridor.

If you have any questions or queries, please contact our team on free phone 0508 NZTA SCI (0508 698 2724) or email us at southerncorridor@nzta.govt.nz. Also feel free to visit us at the Project Office located at 8 Great South Road, Takanini.